Headers
- Chapters
- Pre-Pro [6/8] Part 4 Gantt Chart v3
- 0 0
- 0
However, Ben and Kira set an estimate of 1 full day instead of 1/4 day for "Visuals, Context & Tone".
They have some good ideas for the SpaceShip & Aliens visuals however it will take more time than expected.
So, we decided to split a task into 2: "Visuals" and "Context & Tone".
K6 rebuilt the Gantt chart. Let's have a look:
Scratch inside the frame below to check K6's new Production Plan:
It looks good!
QUIZ: Here are 4 project management questions.
4 good answers win a Bonus Star
Question is loading...
Recap of the correct answers:
Question 1: How long is our new Critical Path?
b. 4 days.
Question 2: Who is contributing to the tasks on the Critical Path?
a. Luke, Ben and Kira all have tasks on the critical path.
Question 3: Are we sure that we can deliver on time?
b. We will revisit our progress at the end of each day and update our Production Plan accordingly.
Question 4: What is a good practice to answer 'Will we deliver on time?':
c. A team exercise to build a 'Risks List' with mitigation plans.
Our new Critical Path is 4 days (in red
■).
Waooo! That's great news!
Pre-Production / [6/8] Part 4 completed