- a detailed schedule, day by day
- who is responsible to deliver each task
- when we need to work on which task
Headers
- Chapters
-
Pre-Pro [5/8] Part 4
Production Plan
- 0 0
- 0
It means 5 days of work.
Scratch inside the frame below to check K6 draft Production Plan:
It looks like it needs iterations...
QUIZ: Here are 4 project management questions.
4 good answers win a Bonus Star
Question is loading...
Recap of the correct answers:
Question 1: What is missing in the draft Production Plan?
b. Dependencies mapping & Capacity planning.
Question 2: Who seems to have too much work on his/her plate?
a. Luke has the most tasks and the highest effort required.
Question 3: How can we determine if the work fits in 4 days?
b. We need to convert the work estimates into time and to identify the critical path.
Question 4: What is the definition of the Critical Path?
c. The sequence of tasks that determines the shortest duration for completing the project.