Recap of the correct answers:
Question 1: In agile methodology, which one of the following is a way to structure work?
b: Initiative / Epic / Story / Task.
Question 2: Who should estimate the time to do a task?
a: The developer responsible for the task execution.
Question 3: What is the usual duration of a SPRINT?
b: 1 to 4 weeks.
Question 4: What is recommended to deliver a risky project on time?
c: Cut scope, request for additional resources, ask for more time.